Why is my P6 slow?
Slow P6 performance usually comes down to a few common causes. Select the symptoms you are seeing to find the likely bottleneck, get practical checks you can run at no cost, and see when your team may have outgrown its current environment.
Written for schedulers and project controls leads using P6 Professional, on its own or connected to EPPM. P6 Professional talks directly to the database; the job services and web tier applies to EPPM web, job services and Citrix. Based on common patterns, not benchmarks.
Where P6 slows down
The P6 setup: complex layouts, filters and grouping can slow things down
The network: network delays make P6 take longer to respond
The job services and web tier (EPPM, Citrix): unmonitored queued jobs can leave you waiting
The database: statistics, indexes and sizing can limit P6 speed
Pick every symptom you are seeing
The path a P6 request takes. The amber bars show where your symptoms suggest you should check first.
What each symptom usually means, and what to check.
Free checks to run first.
Two checks you can run yourself and five to ask IT for. Most slow environments are fixed here.
Checks you can run yourself
- The layout. Open the same project with a minimal layout (no grouping on activity codes, a handful of columns, filters off). If it is much faster, the layout is the cause.
- The schedule log. Far more relationships than activities, or constraints on many activities, make F9 slow on any server. Schedule quality and server capacity are different problems.
Checks to ask IT to run
- Database statistics. They go stale after upgrades and heavy data loads, and stale statistics are the most common cause of environment-wide slowness. Regathering them is free.
- The job services queue. Summarizer, scheduler and export jobs share a tier. If they stack up at the same hour every day, spread the jobs or size the tier.
- Background maintenance and antivirus. P6's own maintenance jobs (SYMON and DAMON) and antivirus scanning of the database and application servers can run into working hours. Move the jobs to a quiet window and exclude the P6 and database paths from real-time scanning.
- Dropped sessions. Disconnections and freezes usually trace to the network path or to software on the workstation that ends idle sessions (VPN timeouts, power settings, security agents), not to P6 itself.
- Response times from where the slow users sit. P6 Professional makes many round trips to the database for one action, so network delay is multiplied. A server upgrade does not fix distance.
When the environment is the problem.
If statistics are fresh, layouts are lean, the queue is clear and network delay is low, the environment may have outgrown what it was installed on. At that point you are choosing between re-sizing it yourself, with the internal hours that carries, or moving it to an environment sized for the schedules you run and re-tuned as it grows.
Two tools put numbers on that choice in about ten minutes: the TCO calculator prices the hours, and the P6 readiness assessment shows where the current setup carries risk.
Take the full checklist with you.
Everything on this page as a printable checklist your team can work through: the free checks in order, what each result means, and the questions to ask before any re-sizing decision. For the long form, the twelve-page field guide covers each check in depth.
If the checks come back clean, the calculator is the next ten minutes well spent.
Frequently asked questions.
Will more hardware fix slow P6?
Only if capacity is the constraint. Stale statistics, heavy layouts and network latency all survive a hardware upgrade untouched. Run the free checks first; buy hardware when the evidence says capacity, not before.
Is P6 just slow with large schedules?
No. P6 runs very large schedules well on an environment sized and tuned for that volume. What is true is that large schedules show up an untuned database and a heavy layout far more visibly than small ones do.
Why are only our remote users slow?
P6 Professional makes many round trips to the database for a single action, so every millisecond of network delay is multiplied. Users far from the database feel distance as slowness. The fix is running the application next to the database and publishing it to the user, not upgrading the server.
Does hosting P6 make it faster?
Hosting by itself, no; a virtual machine is a virtual machine wherever it runs. What makes hosted P6 faster is what surrounds it: sizing for the schedules you run, database tuning as the environment grows, separated job tiers, and application publishing that takes network delay out of the user's path. That is the difference between renting infrastructure and managing the application.